Where under the Contract an action is required to be taken within a specified period, in calculating a period, a day shall be a calendar day and a date shall be a calendar date. When a period is calculated it shall exclude public holidays.
The provisions of the Contract continue to bind the Client and the Architect/Consultant as long as is necessary to give effect to the Parties’ respective rights and obligations.
The Contract supersedes any previous agreement or arrangements between the Client and the Architect/Consultant in relation to the Services (whether oral or written) and represents the entire agreement between the Client and the Architect/Consultant in relation to the Services. All additions, amendments and variations to the Contract shall be binding if agreed in writing by duly authorised representatives of both the Client and the Architect/Consultant.
If any clause or part of any clause of the Contract is ruled by the courts or declared to be invalid or unenforceable in any way, it shall be severed from the Contract and this shall not affect any other clause of the Contract, nor the validity of the remaining clauses of the Contract, which shall remain in full force.
The Contract is subject to the law of England and Wales and the Parties submit to the exclusive jurisdiction of the courts of England and Wales.
Subject to clause 3.1 of the Contract Conditions, to the extent that either Party processes personal data, as part of the Contract, the Party undertakes to do so in compliance with the General Data Protection Regulation (GDPR) and to keep such personal data in a secure technological environment.
The Client shall:
inform the Architect/Consultant of the Project Brief, the Construction Cost, the Project Programme and the Services required and, as soon as reasonably practicable, of any subsequent changes required and agree steps to mitigate the consequences of such changes
provide, free of charge, information in the Client’s possession, or which is reasonably obtainable, and which the Architect/Consultant reasonably advises is necessary for the proper and timely performance of the Services, and the Architect/Consultant shall be entitled to rely on such information
make decisions and give approvals as necessary for the proper and timely performance of the Services
appoint or otherwise engage any Other Client Appointments required to perform work or services under separate agreements and require them to collaborate with the Architect/Consultant. The Client shall confirm in writing to the Architect/Consultant the work or services to be performed by any Other Client Appointments
hold the Other Client Appointments, and not the Architect/Consultant, responsible for the proper carrying out and completion of the work or services entrusted to them under any Other Client Appointments
hold the Contractor(s) appointed to undertake construction works, and not the Architect/Consultant, responsible for the proper carrying out and completion of construction works in compliance with the Building Contract
where the Architect/Consultant is appointed as Contract Administrator for the Building Contract, not deal with the Contractor directly or interfere with the Architect/Consultant’s duties under the Building Contract
not hold the Architect/Consultant responsible for any instructions issued by the Client to the Other Client Appointments or Contractor
pay any statutory charges and any fees, expenses and disbursements in respect of any obligations for planning, building control and other consents.
inform the Architect/Consultant of the Project Brief, the Construction Cost, the Project Programme and the Services required and, as soon as reasonably practicable, of any subsequent changes required and agree steps to mitigate the consequences of such changes
provide, free of charge, information in the Client’s possession, or which is reasonably obtainable, and which the Architect/Consultant reasonably advises is necessary for the proper and timely performance of the Services, and the Architect/Consultant shall be entitled to rely on such information
that planning permission and other approvals from third parties shall be granted at all or, if granted, will be granted in accordance with any anticipated timescale
compliance with any Project Programme and Construction Cost, which may need to be reviewed for, but not limited to:
the competence, performance, work, services, products or solvency of any Other Client Appointments or the Contractor.
The Client shall not disclose Confidential Information unless:
disclosure is necessary to take professional advice in relation to the Contract or the Services
it is already in the public domain other than due to wrongful use or disclosure by the Client
disclosure is required by law or because of disputes arising out of or in connection with the Contract.
In the performance of the Services, and discharging all the obligations under the Contract, the Architect/Consultant will exercise the reasonable skill, care and diligence to be expected of an Architect/Consultant experienced in the provision of such services for projects of a similar size, nature and complexity to the Project. Notwithstanding anything that may appear elsewhere to the contrary, whether under this Contract or otherwise, the Architect/Consultant’s duties and obligations shall be deemed to be subject to the exercise of such reasonable skill, care and diligence and nothing contained in this Agreement or elsewhere shall be construed as imposing on the Architect/Consultant any greater duty than the exercise of such reasonable skill, care and diligence.